Reem Island, Tower R4-A

200 units · 32 floors · Aldar Properties · handover Q2 2029

Readiness confirmed by both channels: engineer 6%, oracle 6%. Stage 1 paid from escrow: 7,920,000 AED.

Readiness

6%

both channels agree

plan: 6% by 31 Jan

Escrow balance

18.4MAED

FAB · Law 3/2015

Units registered

64 / 200

registered with ADREC · demo

Facility placed

30.0MAED

of 132.0M AED · first portion · own participation 20%

Two-channel readiness

payout only on a match
Consultant engineer (escrow)
6%engineer report 28 Jan
Platform oracle (holders)
6%drone 29 Jan · 96 geophotos · BIM check
Tolerance
±1 pt
Result · Stage 1
Match
engineer6%
oracle6%

A mismatch is not a penalty. It keeps the money in escrow until the fact is confirmed, which is why your investors trust the schedule.

Two placements

Unit tokens (CT)64 / 200

buyers and investors in two circuits · residents 35% · international 65%

Construction facility (F)30.0M AED

senior yield 11.5% · repaid from escrow as units sell · 23% of 132.0M AED

Opening a portion is a new issuance: it goes through platform approval, which lands in the E05 admin.

  • Issuance P-011-CT · class CT · resident + international30.4M AED of 132.0M AED
  • Issuance P-011-F · class F · resident + international30.4M AED of 132.0M AED

Readiness over time

plan · engineer · oracle
planengineer (escrow)oracle (holders)
0255075100DecMarJunSepDecMarengineer 6%oracle 6%Dec · plan 0% · engineer 0% · oracle 0%Jan · plan 3% · engineer 3% · oracle 3%Feb · plan 6% · engineer 6% · oracle 6%Mar · plan 10%Apr · plan 14%May · plan 19%Jun · plan 24%Jul · plan 30%Aug · plan 37%Sep · plan 45%Oct · plan 53%Nov · plan 62%Dec · plan 72%Jan · plan 82%Feb · plan 91%Mar · plan 100%
Readiness by month, percent
MonthPlanEngineerOracle
Dec000
Jan333
Feb666
Mar10——
Apr14——
May19——
Jun24——
Jul30——
Aug37——
Sep45——
Oct53——
Nov62——
Dec72——
Jan82——
Feb91——
Mar100——

Milestones and checks

  1. Stage 1 · excavation 6%

    6% of budget · 28 Jan · releases at 6% ready

    Done
    • Engineer 6%Site oracle 6%tolerance ±1Channels agree29 Jan 2026
  2. Stage 2 · foundation 14%

    8% of budget · Mar 2027 · releases at 14% ready

    In progress
  3. Stage 3 · podium 24%

    10% of budget · Jun 2027 · releases at 24% ready

    Planned
  4. Stage 4 · structure 45%

    21% of budget · Dec 2027 · releases at 45% ready

    Planned
  5. Facade and MEP 75%

    30% of budget · Sep 2028 · releases at 75% ready

    Planned
  6. Handover

    25% of budget · Q2 2029

    Planned

Assignments

Buyers resell before handover without queuing for a developer NOC: each transfer is an automated check.

DateUnitPriceFrom → toChecksStatus
3 FebR4A-12041,480,000 AEDinternational → residentKYC ✓ · ADREC ✓ · escrow ✓no NOCdone in 7 min
29 JanR4A-08071,620,000 AEDinternational → internationalKYC ✓ · circuit limit ✓ · escrow ✓no NOCdone in 9 min
22 JanR4A-03111,210,000 AEDresident → internationalKYC ✓ · circuit limit ✓no NOCdone in 8 min

Demo log until the secondary market (E07) records assignments. An assignment used to mean a letter to the developer, an NOC and a 2–5% fee; here it is an automated check at 0.15% per side on founding terms, half of the fee paid to the developer.